January 17, 2013
—
Brady Iandiorio, Higgins, Hopkins, McLain & Roswell, LLC
In a recent case, the Colorado Court of Appeals found that a contractor had a duty to a third party to warn it of a dangerous condition, even after the contractor had completed its work and the owner had accepted the contractor’s work. Collard v. Vista Paving Corp., -- P.3d --, 2012 WL 5871446 (Colo. App. 2012). While not an earth shattering or entirely new concept, the decision rendered in Collard directly accepted the foreseeability rule at the expense of the completed and accepted rule. Id.
In Collard, the City of Grand Junction (“the City”) hired Vista Paving Corp. (“Vista”) to construct two road medians according to the City’s plans and designs. On July 9, 2007, Vista began work on the medians. According to its contract with the City, Vista was responsible for traffic control during construction of the medians. On July 19, 2007, Vista completed its construction of both medians. On that date, the City’s project inspector conducted his final inspection of Vista’s work. The City’s inspector then told Vista that its work had been completed and that Vista was authorized to leave the site. Vista requested permission to remove the traffic control devices to which the City’s inspector agreed. Vista removed all of its traffic control devices.
Mr. Iandiorio can be contacted at iandiorio@hhmrlaw.com