Earlier this year, the Indiana Court of Appeals issued an important opinion that impacts contractors and sureties alike. The decision should give contractors in Indiana pause before ceasing work while a dispute with the owner is pending. Sureties also have been placed on notice that strict compliance with the terms of their bonds is amongst their best defenses to claims made by owners and bond claimants.
In Dave's Excavating, Inc. and Liberty Mutual Insurance Co. v. City of New Castle, Indiana, 959 N.E.2d 369 (Ind. Ct. App. 2012), the contractor (“Dave’s”) was the successful bidder on a public sanitary sewer and water main extension project. Dave's procured a performance bond from Liberty Mutual to guarantee its performance obligations to the owner (the "City"). After encountering what it deemed different subsurface conditions—and indeed after having been previously granted a change order to use excavated materials as backfill in light of the subsurface conditions on site—Dave’s placed the project engineer on notice of a differing site conditions claim. The total claim amounted to an 84% increase in the total contract price. With the claim, Dave's advised the project engineer it was ceasing further work until the project engineer provided direction.
While the project engineer reviewed the claim, it reminded Dave's of its contractual obligation to "carry on the work and adhere to the progress schedule during all disputes or disagreements with the OWNER." A dispute immediately occurred regarding whether Dave's was required to continue to work while the project engineer resolved the differing site condition claim. After Dave's maintained its position that it was not required to continue to work, the project engineer placed it on notice of default and copied the letter to Liberty Mutual.
Brian M. Falcon can be contacted at http://www.frostbrowntodd.com/contact.html