Colorado Supreme Court Weighs in on Timeliness of Claims Against Subcontractors in Construction Defect Actions

March 16, 2017
Jean Meyer - Colorado Construction Litigation

On February 27, 2017, the Colorado Supreme Court announced its decision in the Goodman v. Heritage Builders, No. 16SA193, 2017 CO 13 (Colo. February 27, 2017) case. In ten short pages, the Colorado Supreme Court completely reshuffled Colorado construction law with respect to application of the statutes of limitation and repose on third-party claims in construction defect cases. Specifically, the Colorado Supreme Court overruled a series of earlier Court of Appeals' decisions that found C.R.S. § 13-80-104(1)(b)(II) (“104(1)(b)(II)”) had no effect on the six-year statute of repose. For context, 104(1)(b)(II) permitted third-party actions for indemnity and contribution to toll until ninety days after the claims in the underlying action were resolved by settlement or judgment. In the construction context, 104(1)(b)(II) was intended to allow a general contractor’s claims against liable subcontractors to toll for the statutorily defined period. This allowed the general contractor to first focus its attention on defending the claims against and thereafter to pursue its claims against the subcontractors.

However, beginning in 2008, in the Thermo Dev., Inc. v. Cent. Masonry Corp., 195 P.3d 1166 (Colo. App. 2008) case, the Colorado Court of Appeals began chipping away at the force of 104(1)(b)(II). This trend continued in the Shaw Constr., LLC v. United Builder Servs., Inc., 2012 COA 24, 296 P.3d 145 decision, the Sierra Pac. Indus., v. Bradbury, 2016 COA 132, ­_ P.3d_ decision, and culminating in the Sopris Lodging, LLC v. Schofield Excavation, Inc., 2016 COA 158, reh'g denied (Nov. 23, 2016) decision. Effectively, in these decisions, the Colorado Court of Appeals determined that third-party claims could not be brought beyond Colorado’s six-year statute of repose, regardless if they were brought within the ninety day tolling provision set forth in 104(1)(b)(II).

Mr. Meyer may be contacted at meyer@hhmrlaw.com



714.701.9180

Arrange No Cost Consultation










Subscribe to Construction Defect Journal

Construction Defect Journal Archives - Recent CD News for Construction Claims Professionals

 

Construction Defect Journal is aggregated from a variety of news sources, article submissions, contributors, and information from industry professionals.

No content on this site should be construed as legal advice or expert opinion. By viewing this site you agree to be bound by its terms and conditions

 

Copyright 2017 - Construction Defect Journal – All Rights Reserved