Comparing Contracts: A Review of the AIA 201 and ConsensusDocs - Part II

March 28, 2018
Michael Sams and Amanda Cox – Construction Executive, A publication of Associated Builders and Contractors. All Rights Reserved.

Part II of this three-part series compares and analyzes important contract sections in the AIA 201 (2007 and 2017 versions) and ConsensusDocs (2014 and 2017 versions), including Schedule/Time, Consequential Damages/LDs, Claims and Disputes/ADR. Part I covered Financial Assurances, Design Risk, Project Management and Contract Administration. Part III will cover Insurance and Indemnification and Payment.

SCHEDULE/TIME

Relevant Sections:

  • 2007 & 2017 A201: Section 3.10.1
  • 2014 & 2017 ConsensusDocs: Section 6.2

AIA:

  • Section 3.10.1 of the 2007 A201 requires that the Contractor promptly after being awarded the Contract, prepare and submit a construction schedule providing for Work to be completed within the time limits required in the Contract Documents.
  • This schedule shall be revised at appropriate intervals.
  • The 2017 edition breaks down the schedule to contain date of commencement, interim milestone dates, date of substantial completion, apportionment of Work by trade or building system, and the time required for completion of each portion of the Work.
  • Under section 3.10.2 of the 2007 and 2017 versions, if the Contractor fails to provide a submittal schedule, the Contractor is not entitled to any additional compensation or a time extension based on the Owner’s or the Architect’s slow processing of submittals, regardless of how long they take.

ConsensusDocs 200:

  • The 2017 Contract replaces the term Contract Time and instead requires a “Schedule of the Work…formatted in detailed precedence-style critical path method that (a) provides a graphic representation of all activities and events, including float values that will affect the critical path of the Work and (b) identifies dates that are critical to ensure timely and orderly completion of the Work.”
  • The Constructor must submit an initial schedule to the Owner only before, “first application for payment” and thereafter on a monthly basis. (Section 6.2.1).
  • The Owner is allowed to change the sequences provided in the schedule as long as it does not “unreasonably interfere with the Work.” (Section 6.2.2).

Reprinted courtesy of Michael Sams , Kenney & Sams and Amanda Cox, Kenney & Sams



714.701.9180

Arrange No Cost Consultation










Subscribe to Construction Defect Journal

 

Construction Defect Journal is aggregated from a variety of news sources, article submissions, contributors, and information from industry professionals.

No content on this site should be construed as legal advice or expert opinion. By viewing this site you agree to be bound by its terms and conditions

 

Copyright 2018 - Construction Defect Journal – All Rights Reserved