The recent white paper on Repair Work Endorsements by Jeremiah Welch, drew a storm of responses. Most were appreciative and included follow up questions, but there were those that lamented along the lines of: “How can that be? We’ve been doing it this way for years…”. For the skeptics, the best approach to test the premise of the paper (that most “repair work endorsements” are at best redundant with the PCO extension and at worst restrictive) is to try to formulate a scenario where coverage would be available under a “repair work endorsement” but not under a PCO extension.
Several folks asked about the impact of PCO extensions and repair work endorsements on “punch list” work. “Punch list” work presents a related but different problem. The first issue is understanding what is meant by the term “punch list”. You won’t find that term in an ISO CGL policy. You may find it defined in a construction contract and a Google search will yield several similar definitions. In general, our industry uses the term “punch list” to describe items identified toward the end of a project (often after the contractually defined point of “substantial completion”) which must be completed in order to fully comply with the contract requirements/scope. In short, “punch list” items are items necessary to complete the work.
Mr. Welch may be contacted at jmw@sdvlaw.com