90 and 150: Two Numbers You Must Know

Two stick figures teaching

Two numbers that are critical to the timing and content of any mechanic’s lien are 90 and 150, both found in Va. Code 43-4.

July 22, 2019
Christopher G. Hill - Construction Law Musings

Mechanic’s liens are a big topic here at Construction Law Musings. I’ve discussed everything from the picky nature of this powerful payment tool to the changes that are upcoming on July 1, 2019. Given the strict way that the form and timing of a Virginia mechanic’s lien is so critical, I thought a quick reminder was in order.

Two numbers that are critical to the timing and content of any mechanic’s lien are 90 and 150, both found in Va. Code 43-4. 90 days is the time from the last date of work (not invoicing), or last date of the last month in which work was done given proper circumstances.

The 90 days prescibes the time during which a contractor can properly record a valid lien. This is a hard deadline and is 90 days, not three months. Miss this deadline and no matter what the type of payment that has not been made (something discussed below), the contractor will lose its lien rights. This is the easier of the two numbers to both understand and apply. Count 90 days from last non-corrective or warranty work and that is your hard out for filing.

Mr. Hill may be contacted at chrisghill@constructionlawva.com