Quick Note: Don’t Forget To Serve The Contractor Final Payment Affidavit

Construction worker in site

The contractor final payment affidavit is not a meaningless form.

July 30, 2019
David Adelstein - Florida Construction Legal Updates

If you are a contractor in DIRECT CONTRACT with an owner, serve a contractor final payment affidavit on the owner, as a matter of course, and without any undue delay, particularly if you are owed money and have recorded a construction lien. In numerous circumstances, I like to serve the contractor final payment affidavit with the construction lien.

The contractor final payment affidavit is not a meaningless form. It is a statutory form (set forth in Florida Statute s. 713.06) required to be filled out by a lienor in direct privity of contract with an owner and served on the owner at least 5 days prior to the lienor foreclosing its construction lien. The contractor final payment affidavit serves as a condition precedent to foreclosing a construction lien. Failure to timely serve a contractor final payment affidavit should result in a dismissal of the lien foreclosure lawsuit, presumably by the owner moving for a motion for summary judgment. This should not occur.

Mr. Adelstein may be contacted at dma@kirwinnorris.com



714.701.9180

Arrange No Cost Consultation










Subscribe to Construction Defect Journal

Construction Defect Journal Archives - Recent CD News for Construction Claims Professionals

 

Construction Defect Journal is aggregated from a variety of news sources, article submissions, contributors, and information from industry professionals.

No content on this site should be construed as legal advice or expert opinion. By viewing this site you agree to be bound by its terms and conditions

 

Copyright 2024 - Construction Defect Journal – All Rights Reserved