In Caliber Paving Company, Inc. v. Rexford Industrial Realty and Management, Inc., Case No. G0584406 (September 1, 2020), the 4th District Court of Appeal examined whether a higher-tiered party on a construction project can be held liable for intentional interference with contract when it interferes with the contract between lower-tiered parties even though the higher-tiered party has an economic interest in the contract between the lower-tiered parties.

The Caliber Paving Case

Project owner Rexford Industrial Realty and Management, Inc. owns and operates industrial property throughout Southern California. In 2017, Rexford hired contractor Steve Fodor Construction to perform repaving work at Rexford’s property in Carson, California.

Fodor Construction in turn hired subcontractor Caliber Paving Company, Inc. to perform the repaving work. The subcontract divided the parking lot into four areas, with separate costs to repave each area, and Caliber completed its work in one area in June 2017.

Mr. Murai may be contacted at gmurai@nomosllp.com



714.701.9180

Arrange No Cost Consultation

 

Construction Defect Journal is aggregated from a variety of news sources, article submissions, contributors, and information from industry professionals.

No content on this site should be construed as legal advice or expert opinion. By viewing this site you agree to be bound by its terms and conditions

 

Copyright 2024 - Construction Defect Journal – All Rights Reserved