The CA Supreme Court Grants Petition for Review of McMillin Albany LLC v. Super Ct. 2015 F069370 (Cal.App.5 Dist.) As to Whether the Right to Repair Act (SB800) is the Exclusive Remedy for All Defect Claims Arising Out of New Residential Construction

December 2, 2015
Richard H. Glucksman, Esq., Glenn T. Barger, Esq., Jon A. Turigliatto, Esq., & David A. Napper, Esq. – Chapman Glucksman Dean Roeb & Barger Bulletin

As anticipated in a prior CGDRB 2015 Bulletin that discussed the Fifth Appellate District Court’s noteworthy opinion in McMillin Albany LLC v. Super Ct. 2015 F069370 (Cal.App.5 Dist), the California Supreme Court has granted the petition for review of the McMillin Albany decision. The Supreme Court will attempt to resolve the conflict of authority presented by the Fourth Appellate District Court’s opinion in Liberty Mut. Ins. Co. v. Brookfield Crystal Cove LLC (2013) 219 Cal.App.4th 98 and the Fifth Appellate District Court’s rejection of the Liberty Mutual holding in McMillin Albany.

In Liberty Mutual, the Fourth District Court of Appeal held that compliance with SB800’s pre-litigation procedures prior to initiating litigation is only required for defect claims [violations of SB 800’s building standards] that have not yet resulted in actual property damage. Where damage has occurred, a homeowner may initiate litigation under common law causes of action without first complying with the pre-litigation procedures set forth in SB 800.

Two years later, the Fifth District Court of Appeal, in McMillin Albany, held that the California Legislature intended that all construction defect claims arising out new residential construction are subject to the standards and requirements of the Right to Repair Act [SB800], including specifically, the requirement that the claimant provide the builder with notice and an opportunity to repair prior to filing a lawsuit. According to the Court, SB 800 is the exclusive remedy for all defect claims arising out of new residential construction sold on or after January 1, 2003.

The holdings in Liberty Mutual and McMillin Albany present a conflict of authority that the California Supreme Court has appropriately deemed worthy of review. The parties will now be permitted to file briefs on the merits and amicus briefs will certainly be submitted by the defense and plaintiff bars.

Our firm will be closely monitoring this case, the outcome of which will significantly impact pre-litigation construction defect claims going forward. We will provide updates as to further activities and the Supreme Court’s decision.

Reprinted courtesy of Chapman Glucksman Dean Roeb & Barger attorneys Richard H. Glucksman, Glenn T. Barger, Jon A. Turigliatto and David A. Napper

Mr. Glucksman may be contacted at rglucksman@cgdrblaw.com
Mr. Barger may be contacted at gbarger@cgdrblaw.com
Mr. Turigliatto may be contacted at jturigliatto@cgdrblaw.com
Mr. Napper may be contacted at dnapper@cgdrblaw.com



714.701.9180

Arrange No Cost Consultation










Subscribe to Construction Defect Journal

Construction Defect Journal Archives - Recent CD News for Construction Claims Professionals

 

Construction Defect Journal is aggregated from a variety of news sources, article submissions, contributors, and information from industry professionals.

No content on this site should be construed as legal advice or expert opinion. By viewing this site you agree to be bound by its terms and conditions

 

Copyright 2024 - Construction Defect Journal – All Rights Reserved