As you may know, material prices have been climbing. And they continue to climb based on the volatility of the material market. On top of that, there are lead times in getting material due to supply chain and other related concerns. The question is, how are you addressing these risks? These are risks that need to be addressed in your contract.
As it relates to climbing material prices, one consideration is a material escalation provision. The objective of this provision is to address the volatility of the material market in economic climates, such as today’s climate, where the price of material continues to climb. Locking down a material price today will be different than locking down the same price months from today. This volatility and risk impacts pricing and budgets. Naturally, an owner and contractor would like to be in a position to lock down supplier prices as soon as possible—both to secure pricing and to account for items with long lead times or that recent data forecasts a long lead time due to supply chain concerns. However, this is not always possible or practical and can depend on numerous issues such as when the owner contracts with the contractor, when the owner issues the notice to proceed (and permits are issued), final construction documents and revisions to the construction documents, the type of material, whether there is staging or storage available for the materials, and the current status including climitazation of the project.
Mr. Adelstein may be contacted at dma@kirwinnorris.com