Be Mindful Accepting Payment When Amounts Owed Are In Dispute

Businessman with suitcase stuffed with money

Contractors need to be careful what is signed (or not signed) upon receipt of any payment both during and after completion of work on projects.

August 29, 2022
Nicholas Korst - Ahlers Cressman & Sleight PLLC

After completing work on a project, or even during a project, it is not uncommon for some portion of the contract balance and/or a claim to be in dispute. As a contractor or subcontractor, it is important to be careful what is signed (or not signed) upon receipt of any payment both during and after completion of work on a project. One of the most common documents signed related to a receipt of payment is a lien/claim release document. This can be in the form of a conditional, unconditional, progress and/or final release. The language included in the release document is critically important, especially as it pertains to disputed amounts. As a contractor or subcontractor, if there are known disputes related to amounts owing, whether it be contract balance, disputed change order(s), a delay or inefficiency claim, or any other amounts believed to be owed, it is important to include language in the lien release that expressly carves out the disputed amounts. The same should be done for disputes related to extensions of time. This allows the contractor to accept the payment and release rights for the undisputed work, but continue to reserve its right to pursue the amounts in dispute later. If disputed amounts are not carved out, those amounts may effectively be waived and the subcontractor or contractor may lose all rights to recovery.

As a subcontractor in Alaska recently learned, there are potentially other ways a contractor may waive or lose its rights to recover amounts in dispute – without even signing a waiver or release document. In Smallwood Creek, Inc. v. Build Alaska General Contracting, LLC et al., the general contractor sent the subcontractor a check described as “final payment.” The subcontractor believed it was owed more than what the general contractor had sent and refused to accept the check. Months later, the subcontractor deposited the check. The subcontractor reversed course again and attempted to repay the general contractor the amount deposited. The general contractor refused, claiming the subcontractor’s acceptance of payment constituted satisfaction of all amounts owing to the subcontractor.

Mr. Korst may be contacted at nicholas.korst@acslawyers.com



714.701.9180

Arrange No Cost Consultation

 

Construction Defect Journal is aggregated from a variety of news sources, article submissions, contributors, and information from industry professionals.

No content on this site should be construed as legal advice or expert opinion. By viewing this site you agree to be bound by its terms and conditions

 

Copyright 2023 - Construction Defect Journal – All Rights Reserved