TxDOT: Flatiron/Dragados Faces Default Over Bridge Design Issues

Bridge amsterdam

The Texas Dept. of Transportation ordered a temporary suspension of work on the main cable-stayed portion of the bridge.

September 12, 2022
James Leggate - Engineering News-Record

Texas officials are threatening to replace the contractor building a $930-million bridge crossing the Corpus Christi Ship Channel, alleging the firm has failed to address previously identified safety concerns with the design. In response, the contractor says the state has delayed sharing key engineering information and insists the design is safe.

Reprinted courtesy of James Leggate, Engineering News-Record

Mr. Leggate may be contacted at leggatej@enr.com

Read the full story...



714.701.9180

Arrange No Cost Consultation

 

Construction Defect Journal is aggregated from a variety of news sources, article submissions, contributors, and information from industry professionals.

No content on this site should be construed as legal advice or expert opinion. By viewing this site you agree to be bound by its terms and conditions

 

Copyright 2023 - Construction Defect Journal – All Rights Reserved