A Construction Company was hired as the general contractor and construction manager for the work, who hired the Electrical Contractor to perform the main electrical fit out for the subject premises.

February 14, 2023
Colleen E. Hastie - Traub Lieberman

In a case brought before the New York State Supreme Court, Kings County, Plaintiff alleged injury while performing work at a commercial premises in Brooklyn when he rolled his ankle on a jackhammered/chopped cellar floor slab while carrying a metal pipe from the main floor to the cellar on the subject premises. The property was owned by New York City entities, who were listed as Defendants in the underlying suit. A Construction Company was hired as the general contractor and construction manager for the work, who hired the Electrical Contractor to perform the main electrical fit out for the subject premises. The Electrical Contractor then hired Traub Lieberman’s client, the Electrical Subcontractor, to work on cellar-level conduit, cabling, backboxes, and lighting control systems. The Electrical Contractor, as Second Third-Party Plaintiff, brought suit against the Electrical Subcontractor, as Second Third-Party Defendant, for damages related to the underlying suit.

Ms. Hastie may be contacted at chastie@tlsslaw.com



714.701.9180

Arrange No Cost Consultation

 

Construction Defect Journal is aggregated from a variety of news sources, article submissions, contributors, and information from industry professionals.

No content on this site should be construed as legal advice or expert opinion. By viewing this site you agree to be bound by its terms and conditions

 

Copyright 2023 - Construction Defect Journal – All Rights Reserved