So argued a surety pursuing recovery under its general agreement of indemnity when the indemnitors urged a Louisiana federal court to dismiss the surety’s complaint for failure to join various allegedly required parties as defendants in the litigation.
As part of its court action, the surety moved for preliminary injunction to enforce its collateral security rights. In response thereto, the indemnitors informed the court that if the injunction were to be granted, the indemnitors would “be forced to sell assets that are encumbered by security interests senior to those held by” the surety. In connection therewith, the indemnitors demanded that the other creditors be joined in the action or the lawsuit dismissed. The indemnitors also urged that the public project owner be joined as a party because the surety was seeking proceeds from the project that were still in the possession of the project owner.