Last week we discussed an Owner terminating a Contractor “for cause.” Today, it’s time for a 180: what is your role as the architect when the Contractor is quitting?
First, be aware that there are valid reasons for a contractor to quit within the contract itself. Most of these have to do with either (a) time delays/stand stills or (b) failure of the Owner to make payments as required.
The Contractor can suspend or terminate a contract with the Owner for cause, provided a 7 day written notice is given to Owner and Architect. See A201§14.1.3. (This can be an email notice as all AIA notice clauses now allow).