Two parts of the statute of repose in Pennsylvania have become very controversial in approximately the last five years.
In an unpublished opinion from the Pennsylvania Superior Court handed down on August 31, 2023, a long-standing disagreement about the wording of Pennsylvania's Statute of Repose was finally resolved. In Pennsylvania, “a civil action or proceeding brought against any person lawfully performing or furnishing the design, planning, supervision or observation of construction or construction of any improvement to real property must be commenced within 12 years after completion of construction of such improvement” to recover most forms of damages that are sought in these kinds of cases.
A statute of repose is different than a statute of limitations. A statute of repose is a hard line that does not shift. There is no discovery rule with a statute of repose. Most, if not all, states have statutes of repose for construction. The Pennsylvania statute of repose is among the longest in the country. It can be even longer – up to 14 years – if the injury (including property damage) or wrongful death “shall occur more than 10 and within 12 years after completion of construction.”
Mr. Parisi may be contacted at parisim@whiteandwilliams.com