Court of Appeals Upholds Default Judgment: Serves as Reminder to Respond to Lawsuits in a Timely Manner

Clocks in black background

The case emphasizes the importance of responding to lawsuits and filing motions in a timely manner within the requirements established by Washington law.

October 2, 2023
Anna Basnaw - Ahlers Cressman & Sleight PLLC

In Cyrus Way Partners, LLC. (“Cyrus”) v. Cadman, Inc. (“Cadman”), the primary issue on appeal was whether the trial court erred in denying Cadman’s motion to vacate the default judgment under Civil Rules 55 and 60. A default judgment is a legal ruling that can be entered in favor of the plaintiff when the defendant fails to respond to a lawsuit. If that happens, the court may resolve the lawsuit without hearing from the other side. In Washington, a party typically has 20 days to appear in a suit before being at risk for default judgment. If a default judgment is entered for the plaintiff, the defendant can move to vacate the default judgment, meaning the defendant hopes the court will set aside the default judgment as if it never happened. In this case, Cadman, the defendant, presents several ultimately unsuccessful arguments for why the default judgment in favor of Cyrus, the plaintiff, should be vacated.

Cyrus and Orca Beverage Inc. (“Orca”) are under common ownership. In 2018, Cyrus began a project to build a warehouse for Orca, which included the construction of a large concrete slab. Cadman was hired to supply the concrete. Cyrus hired Olympic Concrete Finishing Inc. (“Olympic”) to finish the concrete. On April 1, 2018, Cadman poured the concrete, and Olympic finished the slab. The next day, Cyrus noticed several problems with the slab, which experts hired by both Cyrus and Cadman opined were caused by an abnormally high air content in the concrete.