New Change Order Bill Becomes Law: RCW 39.04.360

Legislation word on ripped paper

The statute allows for recovery of interest for contractors/subcontractors at 1% per month (12% per year) on the value of the additional work if the statute is violated.

July 8, 2024
Brett M. Hill - Ahlers Cressman & Sleight PLLC

A new statute (RCW 39.04.360) became effective on June 6, 2024, and it applies to extra work performed by contractors and subcontractors on public and private projects in Washington State. The intent of the original bill was to allow contractors and subcontractors to get paid sooner for undisputed additional work. The statute does not apply to private residential projects of 12 units or less. The statute allows for recovery of interest for contractors/subcontractors at 1% per month (12% per year) on the value of the additional work if the statute is violated.

Here are the requirements of the new statute:

  • Public and private owners must issue a change order for the undisputed amount of additional work performed by a contractor, subcontractor, or supplier no later than 30 days after the work is satisfactorily completed and the change is requested by the contractor.
  • General contractors, and subcontractors with lower-tier subs, must issue a change order to their subcontractors impacted by the change within 10 days after receipt of the approved change order from the owner/upper-tier contractor.

Mr. Hill may be contacted at brett.hill@acslawyers.com