Slow Down?

Bid blocks with notebooks and magnifying glass

A general contractor preparing its overall bid for a public project in Jefferson Parish relied in the process on the defendant masonry subcontractor’s bid.

December 3, 2024
Daniel Lund III - Lexology

Absolutely not, said the Louisiana Fifth Circuit Court of Appeal to a masonry subcontractor being sued for allegedly improperly refusing to honor a subcontract bid.

A general contractor preparing its overall bid for a public project in Jefferson Parish relied in the process on the defendant masonry subcontractor’s bid. After a public bid process and receiving the award of the project, the general contractor was informed by the subcontractor that it believed that the unit price form that had been supplied to the sub “contained inaccuracies.” Notwithstanding offers by the GC to endeavor to address the purported “inaccuracies” during the project, most likely by a change order, the subcontractor refused to execute its subcontract. The general contractor then awarded the masonry work to another subcontractor for $368,222 more than the original sub’s bid.

The GC filed suit – for recovery of $368,222 – against the defendant subcontractor during the course of the public project. The defendant sub objected, arguing to the court that the lawsuit was “premature.” At the heart of the prematurity argument: the sub urging that the general contractor filed suit before its right to recover damages had accrued.

Mr. Lund may be contacted at daniel.lund@phelps.com