A federal judge ruled that before the case can be decided, a three-party arbitration must run its course over how many $1-million deductibles the design and construction team owe per claim to project liability insurer Lexington Insurance Co.
August 25, 2025
—
Richard Korman - Engineering News-Record
The $2.1-billion Terminal A replacement project at Newark-Liberty International Airport, open since 2023 in in New Jersey, has turned into a multi-million-dollar legal headache for key companies on the project - the Tutor Perini/Parsons joint venture contractor and its main design subcontractor, STV Engineering.
Mr. Korman may be contacted at kormanr@enr.com