Documents that are created during a project are direct evidence.
I had a case last year in which once again I found myself thinking: if only my client had better documented the verbal agreements, we would have had a much easier time defending his work.
I know this is often easier said than done— you are in the middle of building a project, and you get a call, and you need to keep the project moving. No time for written change directives or a special bulletin. And yet—it is simply amazing to me the number of people who develop “litigation amnesia” about things when a lawsuit is involved.
Your documentation system does not need to be perfect. You can use a simple Field notebook and handwritten notations. A text memo to yourself or, better yet, an email confirmation to the owner/contractor/whoever.