German-Denmark link progresses below the Baltic Sea.
August 3, 2026
—
James Leggate - Engineering News-Record
Work on the $8-billion Fehmarnbelt Tunnel, which is planned to link Germany and Denmark as the world’s longest immersed tunnel, is progressing as crews achieved a milestone last month with the successful immersion of its first precast concrete element. But Danish state-owned project owner Femern A/S says the plan is now running at least two years behind schedule and the tunnel’s road and rail portions will open in two separate stages.