A recent case, Stein v. Reynolds Ventures, Inc., 51 Fla.L.Weekly D1627a (Fla. 2d DCA 2026), discusses this “show cause” statutory procedure.
One of the statutory vehicles to shorten a construction lienor’s statute of limitations to foreclose on a construction lien is through a “show cause” summons that essentially requires the lienor to foreclose on the lien within 20 days from receipt of the “show cause” summons. This is a statutory procedure under Florida’s Lien Law in Fla. Stat. s. 713.21(4). If a lienor receives a “show cause” summons and lawsuit, the lienor should, without delay, counterclaim or file a separate lien foreclosure lawsuit within the 20-day period without exception. This is provided the lienor wants to move forward with its lien. If a lienor does not, the lien will be discharged of record. If you are a lienor and receive a “show cause” summons, please immediately consult with construction counsel that can best advise you and perfect your lien rights.