
This preliminary injunction marks a significant, but interim, victory for the wind energy industry.
On August 6, 2026, the U.S. District Court for the District of Oregon granted a preliminary injunction in Renewable Northwest v. Hegseth, Case No. 3:26-cv-01092-IM, ordering the Department of Defense (DoD) to resume processing wind energy project applications under the existing statutory and regulatory framework and staying DoD’s review freeze pending final adjudication on the merits.
Background
In 2011, Congress created the Military Aviation and Installation Assurance Siting Clearinghouse (Clearinghouse) within DoD to review wind energy projects that might affect military operations. When a wind project developer files an application with the Federal Aviation Administration (FAA), the FAA refers it to DoD to determine whether the project poses an “unacceptable risk to the national security.”
Reprinted courtesy of Victor J. Roehm III, Snell & Wilmer, Christopher P. Colyer, Snell & Wilmer and Sara M. Ajeti, Snell & Wilmer
Mr. Roehm may be contacted at vroehm@swlaw.com
Mr. Colyer may be contacted at ccolyer@swlaw.com
Ms. Ajeti may be contacted at sajeti@swlaw.com