Fall 2024 Legislative Update:

Legislation word on paper in typewriter

A number of other legislative changes may have significant impacts on Washington’s construction industry.

October 28, 2024
Joshua Lane - Ahlers Cressman & Sleight PLLC

Review of (a) RCW 60.30.010-020, (b) RCW 49.17.530, (c) RCW 19.95.020, (d) RCW 39.116.005, et seq., (e) RCW 36.70B.080, and (f) RCW 39.12.010 and .13

While much of the focus on the recent legislative updates has been on RCW 39.04.360, a number of other legislative changes may also have significant impacts on Washington’s construction industry. Six of these changes are summarized below.

A. RCW 60.30.010 and .020 (SSB 6108) – Concerning Retainage on Private Construction, Effective June 6, 2024

Last year, ESSB 5528 imposed restrictions and obligations related to retainage and timing of final payment on private (non-public works) projects. It capped retainage at 5%, required prompt payment on final payments, and required owners to accept a retainage bond on private construction projects, excluding single-family residential construction less than 12 units.

This year, SSB 6108 adds suppliers to the statutes (RCW 60.30.010 and 0.020) pertaining to retainage on private construction projects.

Mr. Lane may be contacted at joshua.lane@acslawyers.com