Subcontractors on public projects in Washington State will no longer be required to wait until final acceptance of the project to get their retainage money. A new statute, which goes into effect on July 23, 2017 and applies only to Washington public projects, will allow subcontractors to get their retainage sooner.
Under prior law, a subcontractor could only get its retainage prior to final acceptance if the general contractor provided a retainage bond to the public owner to secure a release of the general contractor’s retainage and the subcontractor then provided a similar retainage bond to the general contractor in the amount of its own retainage. If the general contractor decided to not provide a retainage bond to the owner, the subcontractor would be forced to wait until final acceptance of the project before it could get paid its retainage.