The decision resolves two issues that have generated significant concern among construction industry professionals since the Court of Appeals issued its opinion on August 1, 2024.
On April 6, 2026, the Colorado Supreme Court issued a unanimous opinion in Ralph L. Wadsworth Construction Company, LLC v. Regional Rail Partners, 2026 CO 19, reversing the Colorado Court of Appeals and providing much-needed clarity regarding verified statements of claim (VSOCs) under the Colorado Public Works Act, C.R.S. §§ 38-26-101 et seq. The decision resolves two issues that have generated significant concern among construction industry professionals since the Court of Appeals issued its opinion on August 1, 2024.
Under C.R.S. § 38-26-107(1), a subcontractor on a public works project may file a VSOC with the contracting public entity for amounts due and unpaid for “…furnished labor, materials, sustenance, or other supplies used or consumed by a contractor or his or her subcontractor in or about the performance of the work contracted to be done or that supplies laborers, rental machinery, tools, or equipment to the extent used in the prosecution of the work….” If a claimant files a VSOC for “an amount greater than the amount due” without a reasonable possibility that the amount is due and with knowledge that the claim is excessive, the claimant “shall forfeit all rights to the amount claimed” and becomes liable for the opposing party’s costs and attorneys’ fees. C.R.S. § 38-26-110.
Ms. McKinlay may be contacted at amckinlay@swlaw.com