Construction Termination Part 3: When the Contractor Is Firing the Owner

Businessman with arms folded

What is your role as the architect when the Contractor is quitting?

August 7, 2023
Melissa Dewey Brumback - Construction Law in North Carolina

Last week we discussed an Owner terminating a Contractor “for cause.” Today, it’s time for a 180: what is your role as the architect when the Contractor is quitting?

First, be aware that there are valid reasons for a contractor to quit within the contract itself. Most of these have to do with either (a) time delays/stand stills or (b) failure of the Owner to make payments as required.

The Contractor can suspend or terminate a contract with the Owner for cause, provided a 7 day written notice is given to Owner and Architect. See A201§14.1.3. (This can be an email notice as all AIA notice clauses now allow).

Ms. Brumback may be contacted at mbrumback@rl-law.com



714.701.9180

Arrange No Cost Consultation










Subscribe to Construction Defect Journal

Construction Defect Journal Archives - Recent CD News for Construction Claims Professionals

 

Construction Defect Journal is aggregated from a variety of news sources, article submissions, contributors, and information from industry professionals.

No content on this site should be construed as legal advice or expert opinion. By viewing this site you agree to be bound by its terms and conditions

 

Copyright 2024 - Construction Defect Journal – All Rights Reserved