Ambiguity in Pennsylvania’s Statute of Repose Finally Cleared up by Superior Court

Woman lying next to clock

Two parts of the statute of repose in Pennsylvania have become very controversial in approximately the last five years.

October 17, 2023
Mark L. Parisi - White and Williams LLP

In an unpublished opinion from the Pennsylvania Superior Court handed down on August 31, 2023, a long-standing disagreement about the wording of Pennsylvania's Statute of Repose was finally resolved. In Pennsylvania, “a civil action or proceeding brought against any person lawfully performing or furnishing the design, planning, supervision or observation of construction or construction of any improvement to real property must be commenced within 12 years after completion of construction of such improvement” to recover most forms of damages that are sought in these kinds of cases.

A statute of repose is different than a statute of limitations. A statute of repose is a hard line that does not shift. There is no discovery rule with a statute of repose. Most, if not all, states have statutes of repose for construction. The Pennsylvania statute of repose is among the longest in the country. It can be even longer – up to 14 years – if the injury (including property damage) or wrongful death “shall occur more than 10 and within 12 years after completion of construction.”

Mr. Parisi may be contacted at parisim@whiteandwilliams.com



714.701.9180

Arrange No Cost Consultation

 

Construction Defect Journal is aggregated from a variety of news sources, article submissions, contributors, and information from industry professionals.

No content on this site should be construed as legal advice or expert opinion. By viewing this site you agree to be bound by its terms and conditions

 

Copyright 2024 - Construction Defect Journal – All Rights Reserved