Unesco Denies Claim It Cleared Construction of Zambezi Dam

Denied with red x through box

Zambezi River Authority head said agency cleared the project.

November 6, 2023
Antony Sguazzin - Bloomberg

Unesco denied that it cleared Zimbabwe and Zambia to proceed with the construction of a $5 billion hydropower dam downstream from the Victoria Falls, which it has designated as a World Heritage Site.

Munyaradzi Munodawafa, chief executive officer of the Zambezi River Authority, said in an earlier interview that Unesco’s World Heritage Committee “agreed that Batoka could go ahead,” referring to the planned dam and 2,400-megawatt power plant on the Zambezi River. Munodawafa didn’t answer calls or text messages to his mobile phone.

“The decision taken by the committee raises several concerns regarding the site, including the inevitable negative impacts of the Batoka Gorge” project, Unesco said in a response to queries.



714.701.9180

Arrange No Cost Consultation

 

Construction Defect Journal is aggregated from a variety of news sources, article submissions, contributors, and information from industry professionals.

No content on this site should be construed as legal advice or expert opinion. By viewing this site you agree to be bound by its terms and conditions

 

Copyright 2024 - Construction Defect Journal – All Rights Reserved